Loretta Lake Drawdown Update

Following is a tentative schedule of the Loretta Lake Dam Project: this can change based on bids and contractor availability, but Jay believes the earliest start for drawing down the lake will be August 15. If for some reason the work cannot proceed on time, the project will be postponed until 2023. We are planning to have Jay and DNR officials speak and answer your questions at the town board meeting June 13th at 5:00 p.m.

DNR Plan Approval ………………………………………………………………….. April 11, 2022

Authorization to Bid From County……………………………………………… April 13, 2022

Final Plan Updates and Commence Advertising ………………………….. April 27, 2022

Bid Opening ……………………………………………………………………………. May 13, 2022

Award by County Board (if needed)……………………………………………. May 19, 2022

Submit Bid Tabulation to DNR for Approval…………………………………. May 23, 2022

Notice of Award from DNR………………………………………………………… June 13, 2022

Pre-Construction Conference ………………………………………………………. July 5, 2022

Notice to Proceed ………………………………………………………………………. July 5, 2022

Begin Construction……………………………………………………………………. July 15, 2022

Begin Drawdown …………………………………………………………………. August 15, 2022

Submit shop drawings for gates……………………………………………… August 15, 2022

Complete drawdown at 6” per day (22days ±)……………………… September 6, 2022

Complete Concrete Repairs……………………………………………… September 15, 2022

Install stop logs in Bay 3 while passing 25% of base flow…….. September 15, 2022

No increase in lake level after…………………………………………… September 25, 2022

Completion of all onsite work except gates…………………………..   October 15, 2022

Complete gate fabrication (allowed 120 days after approval)……….. Dec. 13, 2022

Install gates………………………………………………………………………………. April 3, 2023

Raise lake to Normal Pool……………………………………………………………. May 5, 2023

Final inspection ………………………………………………………………………….. May 5,2023

One-year warranty ……………………………………………………………………. May 5, 2024

The above schedule allows bid review by the County Board, no increase in water levels after September 25th, completion of all onsite work by middle of October, allows 120 days to fabricate the gates after the shop drawings are approved, gates installed by spring of 2023 and water level can then begin to be restored. This schedule will allow the lake to be used for most of the summer of 2022 and refilled by early summer of 2023.